Comcast Tower, Philadelphia
Project Type: Tenant Fit out.
Service: Reactive Coordination
Client: Comcast
**Work performed during employment at StructureTone.
The Comcast
Prefix was in
(………………… what was the story here ………………………. ? )
MEP team has spent 4.5 months on this issue during regular coordination phase
We started working on the case and was able to revolve the issue in 5 days
Process Savings of $51k, on just one Issue.
Comcast Tower - Custom Fittings
We walked an existing building with ______. The risers required a 15” pipe, with 4” horizontal branches. We recognized that no fittings existed to do this, and the standard solution (4 reducers of 2” to the fitting taking up 6’ of pipe each) would be costly, needlessly labor intensive and most importantly would require lower ceilings or a reduction in the unit square footage. We recommended to design a fitting that was able to accommodate the required size change.
We subsequently worked with a manufacturer to create and certify the fitting for the project, saving the client 45,000 sf of rentable space.